The new Trillium line – the diesel train that will run from Bayview to the airport recently passed the first set of tests with flying colours.
Trillium rail line passes crucial test and could be weeks from opening Trillium rail line passes crucial test and could be weeks from opening | CBC News
Trillium Line passes trial run with 99.5 per cent score, Amilcar announces 'with humility and great joy' Trillium Line passes 14-day trial running | Ottawa Citizen
A second seven-day phase of trials began Monday afternoon, when the operator will practise 15 different situations such as what to do if there is a stalled train, a delay caused by problems opening or closing doors, or how to operate when the line is reduced to a single track.
Before the line opens for full passenger service, the city will also run two mock emergencies to help first responders prepare for the LRT, one at the Ottawa airport and one in the tunnel under Dow’s Lake.